Logistics Planning Within the Last Planner System for Highway Construction Projects

Bruno G. Antonini1, Fernanda M. Pimentel2, Marcus C. T. Fireman3, Bernardo M. B. S. Etges4, Frederico R. Campos5, João de Lima Junior6 & Bárbara K. Kronbauer7

1M.Sc. Candidate in Civil Eng. at Federal University of Rio Grande do Sul, Lean Consultant at Climb Consulting Group, Porto Alegre, Brazil. [email protected], orcid.org/0000-0003-4437-4664
2Lean Consultant at Climb Consulting Group, Graduate in Civil Eng. at Pucrs, Porto Alegre, Brazil. [email protected], orcid.org/0000-0003-0230-4326
3PhD Candidate, M.Sc. Eng., Founding-Partner at Climb Consulting Group, Federal University of Rio Grande do Sul, Porto Alegre, Brazil, [email protected] , orcid.org/0000-0001-5843-4715
4PhD Candidate, M.Sc. Eng., Founding-Partner at Climb Consulting Group, Federal University of Rio Grande do Sul, Porto Alegre, Brazil, [email protected] , orcid.org/0000-0002-3037- 5597
5Director Eng. at Neovia Engenharia, Curitiba, Paraná, Brazil [email protected] , orcid.org/0000-0002-5745-7461
6lanning Manager at Neovia Engenharia, Curitiba, Paraná, Brazil [email protected] , orcid.org/0000-0001-5289-0963
7Planning Eng. at Neovia Engenharia, Curitiba, Paraná, Brazil [email protected] , orcid.org/0000-0003-1370-7331

Abstract

This study presents a new Logistics Planning methodology implemented in a highway construction project from May to December 2022. The objective was to analyze the feasibility of using a Logistics Planning method with the help of a Visual Board, in conjunction with the Last Planner System. The research method utilized was the Design Science Research. A 6-step method was developed to enhance the Lookahead Planning routine. After the implementation of the methodology, a decrease in the total and equipment-related impact hours in the productivity fronts was observed, as well as an improvement in the PPC indicator and labour productivity in each service front. It was concluded that the use of Visual Management, combined with Logistics Planning, stimulates the engagement of the operation's employees around the project schedule, increasing the accuracy of the Master Plan.

Keywords

Lean construction Highways, Last Planner System, Visual Management, Lookahead Planning, Logistics Planning.

Files

Reference

Antonini, B. G. , Pimentel, F. M. , Fireman, M. C. T. , Etges, B. M. B. S. , Campos, F. R. , Junior, J. L. & Kronbauer, B. K. 2023. Logistics Planning Within the Last Planner System for Highway Construction Projects , Proceedings of the 31st Annual Conference of the International Group for Lean Construction (IGLC31) , 1291-1302. doi.org/10.24928/2023/0191