TY - CONF TI - Identifying Root Causes of Long Review Times for Engineering Shop Drawings C1 - Taipei, Taiwan C3 - 17th Annual Conference of the International Group for Lean Construction SP - 557 EP - 572 PY - 2009 AU - Chin, Chang-Sun AD - Ph.D., Honorary Fellow, Construction Engineering and Management Program, Department of Civil and Environmental Engineering, University of Wisconsin, Madison, chin2@wisc.edu ED - Cuperus, Ype ED - Hirota, Ercilia Hitomi AB - Every construction project requires approved shop drawings. Design drawings do not show details required for installation, so (sub)contractors cannot construct/install without approved shop drawings. Shop drawings are generally produced by subcontractors and should be reviewed and approved by appropriate parties promptly in order to avoid production delays. Observations on the shop drawing review process reveal that engineering review times of such major construction components as structural steels and reinforcing bars are unnecessarily long and often fail to meet the time frames within which contractors expect to receive responses from the design team. The primary goal of the study is to identify and speculate about possible measures for eliminating the root causes of long review times for engineering shop drawings. Since it is not a simple task to identify and eliminate root causes of any problem because problems are always coupled with their business and work processes, the study uses a systematic problem-solving technique: problem understanding, problem-cause brainstorming, problem-cause data collection and analysis, and root-cause identification. The study reveals that the root cause of long engineering review time is insufficient and unclear information, rather than capability or availability of reviewers. KW - Engineering review KW - problem solving KW - root causes KW - shop drawings PB - T2 - 17th Annual Conference of the International Group for Lean Construction DA - 2009/07/15 CY - Taipei, Taiwan L1 - http://iglc.net/Papers/Details/626/pdf L2 - http://iglc.net/Papers/Details/626 N1 - Export Date: 20 April 2024 DB - IGLC.net DP - IGLC LA - English ER -