TY - CONF TI - Collaborative Planning of Subcontractors Using the Last Planner System and BIM: A Case Study on a Gas Subcontractor in Repetitive Housing Projects C1 - Auckland, New Zealand C3 - Proceedings of the 32nd Annual Conference of the International Group for Lean Construction (IGLC 32) SP - 523 EP - 534 PY - 2024 DO - 10.24928/2024/0222 AU - Brioso, Xaver AU - Delgado, Karla AU - Herrera, Rodrigo F. AU - Lozano, Miguel AU - Bravo, Luis AD - Professor, GETEC Research Group, Department of Engineering, Pontifical Catholic University of Peru, Perú, xbrioso@pucp.edu.pe orcid.org/0000-0002-0174-0241 AD - Researcher, GETEC Research Group, Department of Engineering, Pontifical Catholic University of Peru, Perú, karla.delgado@pucp.pe orcid.org/0009-0004-3627-0982 AD - Assistant Professor, School of Civil Engineering, Pontificia Universidad Católica de Valparaíso, rodrigo.herrera@pucv.cl orcid.org/0000-0001-5186-3154 AD - Lecturer, GETEC Research Group, Department of Engineering, Pontifical Catholic University of Peru, Perú, malozanov@pucp.edu.pe orcid.org/0000-0001-6238-9400 AD - Assistant Professor, GETEC Research Group, Department of Engineering, Pontifical Catholic University of Peru, Perú, bravo.lh@pucp.edu.pe orcid.org/0000-0003-1476-9710 AB - The objective of this study is to adapt the Last Planner System (LPS) for managing subcontractors in natural gas installations within repetitive housing projects, using BIM technology for enhanced modeling and efficiency. Our methodology was applied to a large-scale, multi-family, low-cost housing project in Lima, Peru. Through this application, we achieved high Percent Plan Complete (PPC) values and improved collaborative planning practices. This paper makes distinct contributions to the subcontractor management literature: (1) it demonstrates the practical integration of LPS with BIM to streamline subcontractor activities in a real-world setting; (2) it offers a novel approach for determining optimal Takt Time Planning for daily and weekly schedules, enhancing the predictability and reliability of subcontractor work; and (3) lessons learned from the implementation provide a roadmap that can be adapted to other subcontractor management scenarios. KW - Last Planner System KW - subcontractor management KW - gas facilities management KW - continuous improvement KW - BIM. PB - T2 - Proceedings of the 32nd Annual Conference of the International Group for Lean Construction (IGLC 32) DA - 2024/07/01 CY - Auckland, New Zealand L1 - http://iglc.net/Papers/Details/2302/pdf L2 - http://iglc.net/Papers/Details/2302 N1 - Export Date: 03 April 2025 DB - IGLC.net DP - IGLC LA - English ER -