TY - CONF TI - Kaizen Events for the Development of the Last Planner System® Maturity in a Construction Project C1 - Osaka and Kyoto, Japan C3 - Proceedings of the 33rd Annual Conference of the International Group for Lean Construction (IGLC 33) SP - 471 EP - 482 PY - 2025 DO - 10.24928/2025/0229 AU - Ronceros, Kevin AU - Ronceros, Harold AU - Mio, Luis AU - Miranda, Oscar AU - Chicoma, Jose AU - Soto, Ricardo AD - Production Engineer, National University of Engineering, Lima, Perú, kevin.ronceros.p@uni.pe, orcid.org/0009-0005-1205-3833 AD - Civil engineer, National University of Engineering, Lima, Perú, hroncerosp@uni.edu.pe, orcid.org/0009-0004-4832-9232 AD - Civil engineer, National University of Engineering, Lima, Perú, luis.mio.r@uni.pe, orcid.org/0009-0001-3730-2016 AD - Civil engineer, National University of Engineering, Lima, Perú, omiranda@uni.edu.pe AD - Civil engineer, National University of Engineering, Lima, Perú, jose.chicoma.m@uni.pe AD - Civil engineer, National University of Engineering, Lima, Perú, luis.soto.j@uni.pe ED - Seppänen, Olli ED - Koskela, Lauri ED - Murata , Koichi AB - The construction industry has shown limited advances in innovation and productivity compared to other sectors, despite its global economic relevance. In response to this scenario, companies have adopted practices such as Lean Construction (LC) and tools such as the Last Planner System® (LPS), designed to improve planning and performance in projects. However, the adoption of the LPS is limited by partial implementation that limits the capacity of the system. This research arises as an initiative to develop a structured method that allows a systemic implementation of all the components of the LPS, supported by the Maturity Model (MM) of the LCI lean IPD focused on LPS and Kaizen events to strengthen the adoption of all the components of the LPS. The case study of development during 43 weeks in the construction of the structural shell of the new FIIS-UNI building. During the application of the proposed method, the eight components of the LPS were developed from the development of 43 Kaizen events during the application of the proposed method. This article documents the experience of applying the proposed method and presents a sequential guide of steps to replicate the experience in another construction project. KW - Maturity Model KW - Kaizen events KW - Last Planner System® KW - Integrated Project Delivery KW - Lean Construction. PB - T2 - Proceedings of the 33rd Annual Conference of the International Group for Lean Construction (IGLC 33) DA - 2025/06/02 CY - Osaka and Kyoto, Japan L1 - http://iglc.net/Papers/Details/2391/pdf L2 - http://iglc.net/Papers/Details/2391 N1 - Export Date: 02 June 2025 DB - IGLC.net DP - IGLC LA - English ER -