TY - CONF TI - Site Logistics Planning and Control Using 4d Modeling: A Study in a Lean Car Factory Building Site C1 - Perth, Australia C3 - 23rd Annual Conference of the International Group for Lean Construction SP - 361 EP - 370 PY - 2015 AU - Bortolini, Rafaela AU - Shigaki, Jeferson Shin-Iti AU - Formoso, Carlos Torres AD - M.Sc.,Faculty of Engineering, Building Innovation Research Unit (NORIE), Federal University of Rio Grande do Sul, Porto Alegre, 90035-190, BR, +55 (51) 3308-3518, bortolinirafaela@gmail.com AD - M.Sc. Student,Faculty of Engineering, Building Innovation Research Unit (NORIE), Federal University of Rio Grande do Sul, Porto Alegre, 90035-190, BR, +55 (51) 3308-3518, js_shigaki@yahoo.com.br AD - Associate Professor, Faculty of Engineering, Building Innovation Research Unit (NORIE), Engineering School, Federal University of Rio Grande do Sul, Porto Alegre, 90035-190, BR, +55 (51) 3308-3518, formoso@ufrgs.br ED - Seppänen, Olli ED - González, Vicente A. ED - Arroyo, Paz AB - A major challenge in most construction projects is the need to coordinate a large number of logistic operations in site installation. Despite the growing use of 4D models for planning and coordinating construction activities, the traditional approach adopted for those models is simply to represent the installation sequence defined in a CPM network, which is limited only to conversion activities, whilst a lean perspective suggests that production should also be seen as a flow. The purpose of this paper is to discuss how to plan and control logistics processes in engineer-to-order prefabricated building systems with the use of 4D BIM modeling. This paper investigates the use of BIM to simulate both value-adding and non value-adding activities, such as waiting, inventory and moving materials, as well as site layout. An empirical study was developed in an industrial project for a Car Manufacturing Company that is highly advanced in the implementation of lean production. The scope of the research project includes both the simulation of logistic operations and the monitoring of those operations in the construction site. This paper discusses the benefits and limitations of using 4D BIM for planning and controlling logistics operations in construction sites. Moreover, this study highlighted the need to plan and control site logistics processes hierarchically and focus on logistics critical processes. KW - Building information modeling (BIM) KW - logistics KW - prefabrication KW - 4D modelling KW - visual management. PB - T2 - 23rd Annual Conference of the International Group for Lean Construction DA - 2015/07/29 CY - Perth, Australia L1 - http://iglc.net/Papers/Details/1222/pdf L2 - http://iglc.net/Papers/Details/1222 N1 - Export Date: 20 April 2024 DB - IGLC.net DP - IGLC LA - English ER -